Need Help in Microsoft project 2007(2010)

Asked By 40 points N/A Posted on -
qa-featured

Hi,

I am working with Microsoft project 2007(2010). There is a standard including form in it for an automatization project and now I want to change it. So i need two more options in TAB. One is "Predecessors" link with access database (added by const.) and another one is standard fields, access query which I added by himself.

Can it possible? Please share your opinion and suggestion.

Thanks.

SHARE
Best Answer by May Jratr
Answered By 0 points N/A #152420

Need Help in Microsoft project 2007(2010)

qa-featured

Yes it's possible. You can find the setting within the menu, start with Project>Project information. Fill it with your own project.

There should be a "Task Information Page" pop up, you can input your own data into it.

Best Answer
Best Answer
Answered By 0 points N/A #152421

Need Help in Microsoft project 2007(2010)

qa-featured

Hello Bryan dowdy,

Hope that my message finds you well.
Just to remind you that the predecessors field lists the task ID's, You can use the link tasks command on the edit menu
to link the selected tasks with finish-to-start dependencies and zero lag time. For the fields they contain one kind of information and is part of
table, Project 2007 has several kinds of fields:
-Task and task-timephased fields.
-Resource-timephased fields.
-Assignment and assignment-timephased fields.

Hope this solution will help you and please let me know if you need anything else.
Kind regards,

 